A | Schärding
As part of the extension of the heavy-duty stretch between Wels and Passau, a conversion of Schärding station was envisaged.
The new platform routing and the design of the load-bearing structure to new load standards required a reconstruction of the underpasses and passages in this section of the line. After taking down the original load-bearing structure and widening and amending the structure below, the girders in concrete were erected at a higher position at the sides and pushed in during temporary platform closures - cross traverse.
STEEL WEIGHT: | 227 t |
LENGTH GIRDERS: | |
1) HEM 700 | 23 m |
2) HEM 600 | 14 m |
WIDTH GIRDERS: | |
1) HEM 700 | 16 m |
2) HEM 600 | 19 m |